The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.
The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.      -You have been given a budget of $2500 and instructed to complete the project as quickly as you can using that amount.Which activities do you expedite and what is the final cost and project duration? The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.      -You have been given a budget of $2500 and instructed to complete the project as quickly as you can using that amount.Which activities do you expedite and what is the final cost and project duration?
-You have been given a budget of $2500 and instructed to complete the project as quickly as you can using that amount.Which activities do you expedite and what is the final cost and project duration?

Correct Answer:

verifed

Verified

The project is initially a 49 day ordeal...