Multiple Choice
It is assumed that the job consists of ten steps.The sum of operations times is 30 minutes and the entire job (all ten steps) is done at one station.Then n = 1 and C (the cycle time) is _____ minutes.Therefore,two units are produced per hour.
A) 60
B) 15
C) 30
D) 90