Multiple Choice
Before trying to do detailed,tactical scheduling,_____ should be used to avoid costly mistakes arising from not being prepared with the proper resources at the right time.
A) company planning
B) production scheduling
C) aggregate planning
D) strategic planning
E) enterprise planning
Correct Answer:

Verified
Correct Answer:
Verified