_____ is a higher order planning system than _____.This higher order distribution requirements planning system examines resource availability such as storage space in warehouses,trucking capacity,railroad boxcar availabilities,distribution workforce commitments,and training.It also treats cash flow needed to keep the distribution system performing successfully.


A) DRP;DRP2
B) DRP2;DRP
C) MRP;DRP
D) MRP2;DRP2