Multiple Choice
The first step in the planning hierarchy is _____ planning.
A) production
B) capacity
C) MRP
D) DRP
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q22: RCCP uses approximation to determine whether there
Q23: MRPII is the foundation for Enterprise Resource
Q24: Costs associated with lot-for-lot sizing can be
Q25: Key inputs to the MRP information system
Q26: _ is the function of establishing,measuring,and adjusting
Q28: CRP serves as a precursor of the
Q29: Dependencies are seldom regular because the components
Q30: The multi-level product structure was termed an
Q31: Actual on-hand customer orders provide relatively _
Q32: RCCP is used preliminarily to be certain