Multiple Choice
In an ATO inventory environment,it is often the case that the number of _____ is smaller than the number of _____ products,and master production schedules operate at the components or subassembly levels.
A) finished products;components
B) components;stock
C) components;finished
D) both b and c
Correct Answer:

Verified
Correct Answer:
Verified