Determine Line Efficiency and Relate It to the Balance Delay

Question 89

Essay

Determine line efficiency and relate it to the balance delay measure (given in Equation 17-4) for the following conditions: Total work content is 3 hours;there are 180 stations operating with a cycle time of one minute.Compare the results and meanings of d and L.

Correct Answer:

verifed

Verified

L = Line efficiency = (3)(60)/(180)(1) =...