Multiple Choice
Which of the following is the first step required to utilize PERT-type network models?
A) Draw a precedence diagram.
B) Estimate the time to perform each activity.
C) Detail all of the activities.
D) Meet with suppliers.
Correct Answer:

Verified
Correct Answer:
Verified