Multiple Choice
_____ is associated with the minimum necessary spending on project activities because there is no urgency to complete the project as soon as possible.
A) Crash time
B) Normal time
C) Normal program
D) Abnormal time
Correct Answer:

Verified
Correct Answer:
Verified
Q97: Which are characteristics of good project managers?<br>A)They
Q98: Which of the choices below translates to
Q99: Resource leveling:<br>A)shifts costs among activities.<br>B)does not add
Q100: To spend sensibly to decrease the length
Q101: In general,the most important dimension for evaluating
Q103: PERT and CPM differ regarding the notion
Q104: With really large and complex projects,the PERT
Q105: _ is the interaction of elements that,when
Q106: When using the equation Estimate - Actual
Q107: _ is responsible for managing the inventory