If you are going to crash one particular activity to get the most effect,which one should be chosen?
A) Choose the activity where Dc/Dt is smallest
B) Choose the activity where Dc/Dt is largest
C) Choose the activity where Dc/Dt = 1
D) Choose the activity where Dc/Dt = 0
Correct Answer:

Verified
Correct Answer: