Multiple Choice
The process of readying managers, decision makers, employees, stakeholders, and others for the new system is called ____.
A) user preparation
B) user acceptance
C) start-up
D) installation
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q5: The last of the systems implementation tasks
Q6: _ is the process of readying managers,
Q7: An advantage of buying off-the-shelf software is
Q8: In comparing the pros and cons of
Q9: The logical design specifications that are determined
Q11: Identify the key factors to consider when
Q12: Logical design involves planning the purpose of
Q13: _ allows businesses to subscribe to Web-delivered
Q14: In some cases, organizations decide not to
Q15: When a database fails, failover automatically switches