Multiple Choice
_____ processes include devising and maintaining a workable scheme to ensure that the project addresses the organization's needs.
A) Initiating
B) Planning
C) Executing
D) Monitoring and controlling
Correct Answer:

Verified
Correct Answer:
Verified