Multiple Choice
Administrative activities, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project, are often involved in _____ processes.
A) monitoring and controlling
B) executing
C) initiating
D) closing
Correct Answer:

Verified
Correct Answer:
Verified