After Working with Key Stakeholders to Define Activities and Calculate

Question 25

Multiple Choice

After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to:


A) develop the schedule.
B) control the schedule. 
C) determine their dependencies.
D) estimate the duration of activities.

Correct Answer:

verifed

Verified