    _____ Is the Amount of Time an Activity Can Be
Solved

_____ Is the Amount of Time an Activity Can Be

Question 98

Question 98

Multiple Choice

_____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.


A) Total slack
B) Free float  
C) Backward pass
D) Forward pass

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q3:  An activity is an element of work

Q24:  Network diagrams are the preferred technique for

Q33:  _ is the number of workdays or

Q47:  A schedule management plan includes information which

Q75:  Critical chain scheduling assumes that resources multitask

Q81:  After reviewing the project management plan, project

Q89:  In a network diagram, a(n) _ is

Q95: In project time management, the next step

Q96: AOA network diagrams use only _ dependencies.<br>A)start-to-start<br>B)finish-to-start

Q102: Which of the following types of dependencies

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines