The Process of Controlling Costs Primarily Involves

Question 92

Multiple Choice

The process of controlling costs primarily involves:


A) determining the policies for project costs.
B) managing changes to the project budget. 
C) finalising the procedures for project costs.
D) determining a basis for estimates.

Correct Answer:

verifed

Verified