    Exam 8: Project Quality Management
  5. Question
    _____ Is a Cost That Relates to All Errors Not
Solved

_____ Is a Cost That Relates to All Errors Not

Question 48

Question 48

Multiple Choice

_____ is a cost that relates to all errors not detected and not corrected before delivery to the customer.


A) Prevention cost
B) Appraisal cost  
C) Internal failure cost
D) External failure cost

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q15:  Products that are accepted by project stakeholders

Q16:  A(n)_ is a structured review of specific

Q20:  Complete the formula: sample size = 0.25

Q46: _ is a technique that helps identify

Q49: Which of the following is one of

Q49:  Integration testing involves testing of each individual

Q50: _ involves choosing part of a population

Q52: _, a quality system standard is a

Q55:  The _ means taking responsibility for failures

Q68:  The Six Sigma approach works best for

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines