Multiple Choice
Which of the following is a cause of 'agency problem'?
A) Conflict of interest between buyer and seller due to conflicting goals.
B) Sub-contractors fail to meet project milestones.
C) Detailed project engineering and planning problems.
D) Sub-contractors failure to perform due to poor quality performance.
Correct Answer:

Verified
Correct Answer:
Verified