Multiple Choice
Which of the following is a cause of 'agency problem'?
A) Sub-contractors failure to meet milestone deadlines.
B) Conflict of interest between buyer and seller due to engineering and planning problems.
C) Conflict of interest between buyer and seller due to risk allocation.
D) Conflict of interest between buyer and seller due to poor quality performance.
Correct Answer:

Verified
Correct Answer: