Multiple Choice
Which of the following best explains public procurement 'negotiated procedure with or without prior publication'?
A) Contracting authorities do not need to publish a prior notice before negotiating with suppliers.
B) Contracting authorities cannot negotiate with suppliers.
C) Tenders are submitted from suppliers in a sequence according to the suppliers ranking.
D) Suppliers negotiate with each other.