Multiple Choice
Which of the following best explains 'Kanban'?
A) A form of JIT based upon fixed volume lot delivery.
B) The exact same as just-in-time (JIT) .
C) Where the ordering costs per unit is lowest.
D) A form of JIT based upon fixed volume lot delivery. When a lot is used, the kanban (card) will be sent to the supplier as a signal to replenish that lot
Correct Answer:

Verified
Correct Answer:
Verified