Multiple Choice
Categories of project manager characteristics include each of the following except
A) personal.
B) technical.
C) relational.
D) professional.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q9: Observers have neither interest in nor influence
Q10: Assuming a discount rate of 8 percent,what
Q11: A project involving renovations due to a
Q12: Individuals or organizations who are affected by
Q13: A sentence or short paragraph written by
Q15: A methodology used in incorporating the requirements
Q16: A use case is a technique used
Q17: Which of the following describes the work
Q18: Technology employed in projects should not determine
Q19: According to Wheelwright and Clark,which of the