Multiple Choice
Purposes for identifying stakeholders include each of the following except
A) knowing the individual to blame if the project fails.
B) improving working conditions.
C) streamlining business and project processes.
D) stabilizing the project when things go in the wrong direction.
Correct Answer:

Verified
Correct Answer: