Multiple Choice
A document that specifies a project's requirement in a complete,precise,verifiable manner and includes the procedures for determining whether the requirement is satisfied best defines
A) specifications.
B) request for proposal.
C) request for quotation.
D) project charter.
Correct Answer:

Verified
Correct Answer:
Verified