A Part of the Project Management Plan That Is the Baseline

Question 35

Multiple Choice

A part of the project management plan that is the baseline of the scope of a project and includes the project scope document,WBS,and WBS dictionary best defines


A) network diagram.
B) definitive schedule.
C) WBS.
D) scope baseline.

Correct Answer: