Multiple Choice
Which of the following provides the descriptions of activities that can be easily understood by the team members who are scheduled to carry out those activities?
A) WBS dictionary
B) WBS scope
C) WBS communication plan
D) WBS resource plan
Correct Answer:

Verified
Correct Answer:
Verified