Multiple Choice
Defining each risk by a set of standard parameters including likelihood or probability,severity or impact,detection process,and mitigation plans best defines
A) quantitative risk management.
B) qualitative risk management.
C) risk probability.
D) risk regression.
Correct Answer:

Verified
Correct Answer:
Verified