Multiple Choice
Risks associated with costs can be reduced by each of the following except
A) considering many design alternatives before choosing the design.
B) creating a project schedule and striving to adhere to it.
C) identifying and monitoring the key cost drivers.
D) identifying critical tasks and their interdependencies.
Correct Answer:

Verified
Correct Answer:
Verified