Multiple Choice
A comparison of the contingency reserves of schedule,resources,and budget at a particular time during the progress of a project with the original schedule,resources,and budget to determine if there are enough reserves in schedule,resources,or budget best defines
A) total operating cost.
B) feasibility study.
C) reserve analysis.
D) risk analysis.
Correct Answer:

Verified
Correct Answer:
Verified