Causing a delay to the whole project is called


A) acquired float.
B) total float.
C) accumulated float.
D) negative float.

Correct Answer:

verifed

Verified

Related Questions

Q1: Which of the following is used to

Q2: A method of planning and managing projects

Q4: A scheduling approach driven by the quantity

Q5: PDM is useful because it provides<br>A)the start

Q6: A project management tool used to schedule,organize,and

Q7: Which of the following is the delivery

Q8: Which of the following is used in

Q9: The total project duration is the sum

Q10: In PDM,an activity can have predecessors with

Q11: One very important purpose of constructing and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines