    Negative Slack Can Occur Due to
Solved

Negative Slack Can Occur Due to

Question 78

Question 78

Multiple Choice

Negative slack can occur due to


A) unavailability of resources.
B) resources were either incorrect or did not do their job right.
C) some activities slipped during project execution.
D) all of the above.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q70: Capacity measures how early or late an

Q71: Basic reasons for creating dependencies of project

Q72: What is negative slack? Why does it

Q73: For an activity,assume the early start is

Q74: When constructing the PDM,an activity can have<br>A)predecessors

Q75: Causing a delay to the whole project

Q76: SAP PS is a free,web-based project software

Q77: Popular project management software packages include each

Q79: A work breakdown flowchart is useful for

Q80: If the early start for an activity

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines