Multiple Choice
In CCPM,a definite amount of time that can be added at the end of the project is called
A) project buffer.
B) feeding buffer.
C) relaxed capacity.
D) safety buffer.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q18: If prototype testing can be started only
Q19: Project Evaluation and Review Technique is a
Q20: Which of the following was chosen by
Q21: If the optimistic time is 3,the most
Q22: The standard deviation of the critical path
Q24: Dependencies involving relationships between the project and
Q25: The CCPM method modifies the project schedule
Q26: Benefits of networking project activities include<br>A)an estimate
Q27: Which of the following is a free,web-based
Q28: Contraction rate is the duration at which