True/False
If cost variance is positive,it means that performing the activity cost more than the planned or budgeted cost.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q22: Estimating is the process of determining the
Q23: Steps taken to complete resource planning include<br>A)list
Q24: Earned value is the budgeted amount of
Q25: Resources include<br>A)people.<br>B)facilities.<br>C)equipment.<br>D)all of the above.
Q26: The amount of cost budgeted for completed
Q28: Office supplies,telephone,and utilities are examples of direct
Q29: The ratio of earned value to actual
Q30: Which of the following compares cost deviations
Q31: In a software project,the cost of designers,developers,and
Q32: Duration is defined as the total span