    If Schedule Variance Is Negative,it Means It Took Longer to Perform
Solved

If Schedule Variance Is Negative,it Means It Took Longer to Perform

Question 60

Question 60

True/False

If schedule variance is negative,it means it took longer to perform the activity than planned.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q55: Which of the following provides the efficiency

Q56: The best estimate of the total cost

Q57: Baseline management focuses on identifying,evaluating,documenting,and managing changes.

Q58: CPI is the most important tracking metric

Q59: Incurred costs that cannot be changed by

Q61: Identify three opportunities created by embracing scope

Q62: Project costs do not contribute to the

Q63: A set of approval stages that are

Q64: A negative cost variance indicates the project

Q65: Sunk costs are entirely linked to the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines