Multiple Choice
Which of the following compares actual and baseline duration?
A) cost variance
B) resource variance
C) duration variance
D) work variance
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q38: Identify five benefits of EVA.
Q39: A method to flatten the schedule when
Q40: Methods employed in estimating costs include each
Q41: Unquantifiable costs relating to an identifiable source
Q42: ROME provides a rough estimate of what
Q44: The process of determining the cost of
Q45: In fixed duration,the amount of work is
Q46: The cost resource variance is the schedule
Q47: The ratio of earned value to planned
Q48: If the SPI is equal to 1.5,then