Solved

Which of the Following Project Audit Report Questions Addresses PMBOK's

Question 51

Multiple Choice

Which of the following project audit report questions addresses PMBOK's human resources management knowledge area?


A) Are quality metrics developed,measured,and monitored?
B) Are minutes of meetings stored and distributed?
C) Is the project team being recognized and rewarded?
D) Does the project plan consist of a contingency plan?

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions