Multiple Choice
A Gantt chart is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a ____ format.
A) calendar
B) line graph
C) bar graph
D) pie chart
Correct Answer:

Verified
Correct Answer:
Verified