menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Technology
  4. Exam
    Exam 5: Project Scope Management
  5. Question
    Which Task Is at the Lowest Level of the WBS
Solved

Which Task Is at the Lowest Level of the WBS

Question 64

Question 64

Multiple Choice

 Which task is at the lowest level of the WBS?


A) variance
B) objective
C) deliverable
D) work package

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q59:  Project scope statements must include the project

Q60:  A hierarchy is used to show the levels of _

Q61:  _ is a process for identifying and

Q62:  _ is the tendency for project scope

Q63:  Which technique is used for creating a WBS

Q65:  The project scope statement should reference supporting

Q66:  _ is a technique that uses branches

Q67:  The main purpose of the WBS is

Q68:  What process involves formal acceptance of the

Q69:  What is a table that lists requirements,

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines