Short Answer
When using project management software, estimates of work time should be entered only at the work package level; the rest of the WBS items are just groupings or _____ tasks.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q33: Describe the process of scope validation.
Q34: _ is the difference between planned and
Q35: A(n) _ is a table that lists
Q36: Some organizations prescribe the form and content
Q37: What is a work breakdown structure? What
Q39: What is scope creep?<br>A) the tendency for project
Q40: A work package is a task at
Q41: Which approach for constructing a WBS uses
Q42: _ includes the processes involved in defining
Q43: List and briefly describe the six main