Multiple Choice
In project schedule management, which process involves estimating the number of work periods that are needed to complete individual activities?
A) defining activities
B) sequencing activities
C) planning schedule management
D) estimating activity durations
Correct Answer:

Verified
Correct Answer:
Verified