Multiple Choice
In project schedule management, which process primarily involves checking and managing changes to the project schedule?
A) estimating activity durations
B) developing the schedule
C) controlling the schedule
D) estimating activity resources
Correct Answer:

Verified
Correct Answer:
Verified