Which statement is true of a order of magnitude estimate?
A) It is used to allocate money into an organization's budget.
B) It provides an estimate of what a project will cost.
C) Its timeframe is always less than a year prior to project completion.
D) It is a type of estimate that is done in the final stages of a project.