menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Technology
  4. Exam
    Exam 7: Project Cost Management
  5. Question
    What Is Another Term Used for Budget
Solved

What Is Another Term Used for Budget

Question 30

Question 30

Multiple Choice

 What is another term used for budget?


A) earned value
B) actual cost
C) indirect cost
D) planned value

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q25:  Project managers must conduct cash flow analysis

Q26:  Which type of estimate uses the actual

Q27:  Determining the budget involves allocating the project

Q28:  Which costs are difficult to measure in

Q29:  The _ is the measure of work

Q31:  _ is a project performance measurement technique

Q32:  The primary output of the planning cost

Q33:  _ costing considers the total cost of

Q34:  _ costing helps to see a big-picture

Q35:  Which process helps develop an accurate projection

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines