Multiple Choice
Which is true of the schedule performance index (SPI) ?
A) It can be used to estimate the projected time to complete the project.
B) It means that a project is behind schedule if an SPI is greater than one.
C) It means that a project is ahead of schedule if SPI is lesser than one or hundred percent.
D) It is the ratio of planned value to actual costs.
Correct Answer:

Verified
Correct Answer:
Verified