Multiple Choice
Which tool is a column chart that shows the number of resources assigned to a project over time?
A) responsibility assignment matrix
B) resource histogram
C) RACI charts
D) organizational breakdown structure
Correct Answer:

Verified
Correct Answer:
Verified