Multiple Choice
What process involves deciding how to approach and plan the risk management activities for the project?
A) identifying risks
B) planning risk management
C) performing qualitative risk analysis
D) performing quantitative risk analysis
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q8: Large, complex projects involving leading-edge technologies often
Q9: The main outputs of which process include a
Q10: Unknown risks can be managed proactively.
Q11: The risk register can be created with
Q12: Potential problems that might occur on the
Q14: Which is a fact-finding technique that can
Q15: Project teams sometimes use _, which are
Q16: Risks can have both negative and positive
Q17: _ helps professionals to see the effects
Q18: Identifying risks is a subprocess of the