Multiple Choice
Which process involves numerically estimating the effects of risks on project objectives?
A) performing qualitative risk analysis
B) planning risk responses
C) identifying risks
D) performing quantitative risk analysis
Correct Answer:

Verified
Correct Answer:
Verified