  5. Question
    Which Action Involves Eliminating a Specific Threat, Usually by Eliminating
Solved

Which Action Involves Eliminating a Specific Threat, Usually by Eliminating

Question 78

Question 78

Multiple Choice

 Which action involves eliminating a specific threat, usually by eliminating its causes?


A) risk avoidance
B) risk acceptance
C) risk transference
D) risk mitigation

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q69:  The main output of qualitative risk analysis

Q70:  Risk _ refers to reducing the impact

Q71:  What is the first step in a

Q72:  A risk-seeking person prefers outcomes that are

Q73:  A(n) _ documents the procedures for managing

Q74:  _ are predefined actions that the project

Q75:  _ risks are risks that remain after

Q76:  Risk utility rises at a decreasing rate

Q77:  Which action applies to positive risks when the

Q79:  Which action involves reducing the impact of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines