True/False
A company is considering whether to purchase or lease a piece of equipment for an upcoming project. The cost to purchase is $10,000 plus $100 per day to operate or $500 per day to lease (including operating costs). If the company anticipates using the equipment for a total of 20 days, they will be indifferent as to whether or lease or purchase it.
Correct Answer: