Multiple Choice
What process involves determining everyone involved in the project or affected by it, and determining the best ways to manage relationships with them?
A) identifying stakeholders
B) planning stakeholder management
C) managing stakeholder engagement
D) controlling stakeholder engagement
Correct Answer:

Verified
Correct Answer:
Verified